On March 22nd, 2025 the ‘Irish Independent’ newspaper
reported that Eirgrid
has confirmed that the 600 MW Shannon LNG gas power plant given
planning
permission by An Bord pleanála on March 13th 2025,
and which has a 10-year auction capacity contract of
353MW worth €494m from EirGrid, is a cost that
will ultimately be paid by households and businesses through their
electricity bills.
Local groups 'Safety Before LNG' and 'FutureProof Clare', in their
joint submission to the
Review of Large Energy Users Connection Policy by
the Commission for the Regulation of Utilities (CRU) have accused the
CRU of not protecting domestic customers, whose electricity bills are
destined to increase each time more Large Energy Users, especially data
centres, are connected, by a distortion of the Auction Capacity
process.
The Joint Submission stated the following:
The Commission for the Regulation of Utilities (CRU) claims that its
Mission Statement is to protect the public interest in Water, Energy
and Energy Safety, guided by strategic priorities which include driving
a low carbon future and protecting customers.
However, we are deeply concerned that the CRU in this proposed decision
is deliberately and disingenuously
- breaching its Obligations under Section 15.1 of
the Climate Action and Low Carbon Act 2015 as amended which states that
“a relevant body shall insofar as practicable, perform its function in
a manner consistent with …. (e) the objective of mitigating greenhouse
gas emissions and adapting to the effects of climate change in the
State” and
- Not protecting domestic customers, whose
electricity bills are destined to increase each time more Large Energy
Users, especially data centres, are connected by a distortion of the
Auction Capacity process.
1. CRU ignoring its
Climate obligations as a relevant body under Section 15 of the Climate
Action and Low Carbon Act 2015 as amended.
From the example of the Shannon LNG 600MW gas-fired power plant granted
planning
permission by An Bord pleanála on March 13th 2025,
having been awarded a 10-year auction capacity contract of
353MW worth €494m from EirGrid, we note that
EirGrid took no account of how the emissions from this power plant
would be mitigated. It is unconscionable that An Bord Pleanááa would
rule that the emissions would be partly mitigated by participation in
the European Union Emissions Trading System Scheme. So we have a case
where Shannon LNG is able to claim support for its power station
planning application having been awarded 353MW of auction capacity by
EirGrid and then where the Board has to rule on how its emissions could
be mitigated - not even to mention the fact that the overall masterplan
mentioned throughout its planning application is for 8 data centres
powered by US fracked gas imports.
The proposed CRU policy (page 2) states:
It is expected that data centres will represent 30% of national
electricity demand in Ireland by 2030 if no additional data centres are
contracted over and above what is already signed up.
However, the plan this proposed document on LEU’s is for is “the
development of data centre infrastructure“ (pg 3) which will therefore
surely encourage more data centre development beyond the data centres
that are already “signed up”.
The proposed policy admits (pg 6-7) “The pace at which new electricity
demand is being sought by data centres is faster than the pace of
network infrastructure delivery and the development of new generation
capacity.”
The CRU aim to resolve this problem, where data centres will be
expected to use a disproportionate amount of energy beyond the current
capacity of the existing energy infrastructure by proposing that “Data
centres connecting to the electricity network will be required to
provide dispatchable onsite or proximate generation and/or storage
capacity” (pg 11).
However, despite the stated role of the CRU to protect the public
interest in terms of energy they state (pg 12) “The CRU is not
proposing to introduce any new decisions relating to connections to the
gas network as part of this review process.
We strongly object to this cop-out. The CRU cannot defer to Gas
Networks Ireland (GNI) in terms of regulation of electricity. GNI, on
its website, states that it is a business. It is therefore designed to
make a profit with a vested interest in growing and developing. The
CRU’s role is to regulate GNI and ensure that any development is in
line with legal climate obligations and in the public interest. The
current proposed LEU policy refuses to regulate GNI, is not aligned
with the Climate Act, the Climate Action Plan and is certainly not in
the public’s best interest. Rather it is aligned more with the needs of
data centres, and has decided that to resolve the issue of big tech
needing more energy, it will pave the way for LEU’s to increase demand
for fossil fuels through the proposed
“Requirement to provide onsite or proximate generation” (pg 12) for
LEU’s.
Our concern is that this approach is being replicated across all
individual planning applications for gas-fired power stations with no
strategic environmental assessment of the overall climate impacts of
the large-scale rollout of gas-fired power stations in line with the
rollout of the large-scale energy users such as data centres.
And no account has even been taken of the stark warning in the joint
report from the Irish Fiscal Advisory Council and
Climate Change Advisory Council that Ireland is already facing
“staggering payments” of between €8 and €26 billion to other European
Union member states if climate targets are missed.
An Bord pleanála stated in its decision
Order 7:
Operation of the proposed power plant would give rise to an increase in
operational greenhouse gas emissions with resulting impacts on the
achievement of EU and National climate change and carbon emission
reduction targets. The impacts from such activities would be adequately
mitigated by:
- The role of the Combined Cycle Gas Turbine in
the overall energy generation sector and in facilitating renewable
generation capacity and the transition to a low carbon system;
- Displacement of potentially more carbon
intensive power generation;
- Operation in the European Union Emissions
Trading System scheme;
- Embedded design mitigation, including high
efficiency and ability to operate at a low minimum generation capacity
means that it will be dispatched before less efficient plants;
- Availability of battery storage;
- Stated ability to transition to alternative low
carbon fuels/hydrogen
2. Distortion of the
Auction Capacity process
On March 16th, 2025, the Irish Independent newspaper
reported that from 2018 to 2024, a report by UK
analysts Aurora Energy Research and Beyond Fossil Fuels (BFF) found
that
€6bn in capacity payments were
awarded for gas generation in Ireland, about €1bn a year and
that Billpayers are already paying further monies on top of these
charges. The newspaper reported that billpayers have also paid an
additional €1.18bn over the three years to September in a so-called
temporary generation levy to cover four new gas generation units. The
cost of the auction capacity for LEUs should not be socialised across
to domestic consumers and this decision paper has ignored these
downstream impacts. This is the full story:
Consumers’
energy bills set to rise further as more data centres will add to costs
Commission for Regulation of Utilities confirms data centres and power
suppliers are eligible for big capacity payments
After recent price hikes by energy providers,
further data centres and
power plants are coming on stream which are set to see bills rise
further. Stock image
John Reynolds
Sun 16 Mar 2025
Household electricity bills are effectively subsidising data centres by
hundreds of millions of euro a year, an investigation by the Sunday
Independent can reveal.
The energy regulator, the Commission for Regulation of Utilities (CRU),
has confirmed that data centres and power suppliers are eligible for
hundreds of millions of euro in so-called capacity payments for
generating electricity, some of which is gas-powered.
Such payments have increased significantly since 2007 and are
contributing to higher bills. They are paid to electricity providers
for being available to supply power when it is needed, and a component
of the price of electricity.
Now, after a suite of price hikes by energy providers, further data
centres and power plants are coming on stream which are set to see
bills rise further.
Our analysis, in collaboration with an environmental campaign group and
a firm of energy analysts, found €600m in capacity payments awarded to
or applied for by three companies supplying or running data centres.
The largest recipient is Lumcloon Energy, which built a 275MW gas power
station, for which it was awarded €364m in such payments when it was
completed last year. In December it submitted plans to build a €1bn
250MW data centre nearby, with on-site fuel cells, solar and battery
power, which would also be eligible for subsidies.
Bord Gáis is due €132m in payments later this year for a power station
being built beside a west Dublin cluster of data centres.
Some €101m in capacity payments was applied for by two Echelon Data
Centres facilities there and in Wicklow scheduled between 2023 and 2027.
Ireland already has some of the highest electricity prices in Europe
and new electricity peak demand records were hit during recent cold
snaps
Dublin-based Echelon Data Centres said it had bid for capacity payments
but clarified that its gas-powered generation facilities in Arklow and
Dublin haven’t been built yet, so it has not received any money.
Lumcloon Energy said its gas plant provides backup for wind, claiming
its power is cheaper than from temporary generation. Its data centre’s
on-site power plan is innovatively market-leading, it added.
A spokeswoman for Bord Gáis said that its Profile Park facility is
currently being built, due for completion later this year. It has a
contract making it eligible for capacity payments from later this year,
she added.
Ireland already has some of the highest electricity prices in Europe
and new electricity peak demand records were hit during recent cold
snaps.
SSE Airtricity recently announced a price hike of 10.5pc taking effect
next month, equating to €171 on the average annual bill. It cited a
20pc increase in network charges last October, and capacity payments
are a component of these as well as overall power costs.
Daragh Cassidy of price comparison site Bonkers.ie said: “Data centres
use more than a fifth of all electricity nationwide and impact peak
demand, which is typically when the least efficient and most expensive
gas-fuelled suppliers are needed, so it’s ridiculous to think they
don’t impact on prices.”
A spokesman for Energy Minister Darragh O’Brien said: “The CRU decides
on the power procured in the capacity market. It also has
responsibility for the setting of electricity connection policy.”
Ger Fulham, managing director of Dublin-based energy procurement
consultants Kore Energy, said capacity payments are one of a number of
regulatory charges that have collectively doubled between 2019 and this
year, according to his own analysis. Those charges make up about a
fifth of recent price rises, he added. He said that between 2007 and
2018 billpayers paid about €5bn in capacity payments, an average of
€454m a year.
Then, from 2018 to 2024, a report by UK analysts Aurora Energy Research
and Beyond Fossil Fuels (BFF) found that
€6bn in capacity payments were awarded for
gas generation in Ireland, about €1bn a year.
Gas-powered energy generation is more expensive than renewable power
and is vulnerable to price surges
Billpayers are already paying further monies on top of these charges.
They’ve paid an additional €1.18bn over the three years to September in
a so-called temporary generation levy to cover four new gas generation
units, Mr Fulham explained.
Gas-powered energy generation is more expensive than renewable power
and is vulnerable to price surges — such as those seen since the war in
Ukraine — yet it is predicted to increase nationally, according to the
CRU. “On-site generation will be eligible to participate in the
capacity market. Peak day gas demand is predicted to grow due to
increased gas-fired electricity to meet demand on days of low renewable
availability,” a CRU spokeswoman said.
The report also found that payments bid for by and awarded to
gas-powered electricity suppliers cover an increase in new power
stations’ generation capacity here by 3.9GW, about 80pc more than the
current 4.7GW. Eirgrid capacity statements also point to an increase
equal to four or five new large gas power stations being required by
2030.
Data centres’ power use is forecast to increase to 31pc by 2032. It has
risen more than 20pc a year since 2015, according to research by
University College Cork published in December. There are 89 data
centres in Ireland, mostly concentrated in and around Dublin, with
around 11 in construction and applications for at least 30 more to be
built, according to planning applications and industry data.
Their use of electricity has also effectively cancelled out all of the
growth in renewable electricity from sources such as wind, critics have
previously pointed out.
Partly as a result of this, BFF’s analysis found that Ireland has the
highest per capita existing and planned gas power plant capacity in
Europe. Out of the six markets the report analysed, Ireland also had
the highest overall level for such payments, about 70pc higher than the
next-ranked, Britain.
Critics have called for government action to bring down electricity
prices, including power market reform and limits on data centre
expansion.
Social Democrats spokeswoman on climate Jennifer Whitmore said: “The
Government has rolled out the red carpet to data centres without any
strategic analysis of the overall impact on our grid, energy security
and ability to meet emissions targets. Without any transparency on
their impact on prices, data centres’ extreme levels of energy demand
could only be forcing our already high energy prices up even further.
The Government should be working to bring them down.”
Rosi Leonard, data centre campaigner at Friends of the Earth, said: “We
need to start talking about capacity limitations on these energy users
who are rapidly outpacing renewables generation, and can now make a
handsome sum from capacity markets.”
The campaign group’s head of policy Jerry Mac Evilly said regulation of
the electricity market needs “a fundamental overhaul”, and contradicted
the Programme for Government’s commitment to decisive action to reduce
reliance on fossil fuels.
“The capacity market is locking us into more, not less, gas
infrastructure,” he added.
On March 22nd, 2025 the ‘Irish Independent’ newspaper further
reported that Eirgrid has confirmed that the 600
MW Shannon LNG gas power plant given planning
permission
by An Bord pleanála on March 13th 2025, and has a 10-year auction
capacity contract of
353MW worth €494m from EirGrid, is a cost that will
ultimately be paid by households and businesses through their
electricity bills. This is the full story:
Shannon LNG
power plant’s €494m capacity contract will be paid for by customers’
bills

An artist's impression of Shannon LNG at Ballylongford-Tarbert landbank
.
John Reynolds
Sat 22 Mar 2025 at 02:30
Eirgrid has confirmed that the Shannon LNG gas power plant given
planning permission this week has a 10-year capacity contract worth
€494m, a cost that will ultimately be paid by households and businesses
through their electricity bills.
Capacity payments, which have increased significantly since 2007, are
paid to power suppliers for being available to supply electricity when
needed.
“Shannon LNG was successful in the 2026/2027 T-4 capacity auction for
two units, each of which was awarded 176.6 MW at a price of
€140,000/MW/year, for a duration of 10 years,” an Eirgrid spokesman
said.
The contracted power price is at the highest level of such rates,
according to a recent analysis by the environmental campaign group
Beyond Fossil Fuels (BFF) and Aurora Energy Research.
Out of six markets analysed, Ireland had the highest overall level for
capacity payments, about 70pc higher than Britain. It also found that
Ireland has the highest existing and planned gas-power plant capacity
in Europe per head of population.
Shannon LNG’s parent company New Fortress Energy did not respond to
calls and emails. A recent filing it made to the US Securities and
Exchange Commission (SEC) confirmed its capacity contract, but did not
state the value. The contract requires the plant to begin delivering
power to the grid next year.
The company has been given permission for a battery storage system, as
well as the power plant, on a 630-acre site in Kerry. It separately
received planning permission for five kilometres of 220kv underground
cabling and fibre optic cables.
According to the SEC filing, Klondike, a subsidiary of New Fortress
Energy, plans to build and operate large data centres in Brazil,
America and Ireland.
Last week the Sunday Independent revealed that three companies
supplying data centres, or with plans to build them in Dublin, Wicklow
and Westmeath, qualified for €600m in capacity payments. Adding Shannon
LNG to the list would bring the total to €1.1bn.
Data centres’ power demands are increasing, and Eirgrid forecasts
suggest they will account for up to 31pc of national electricity usage
by 2032, from a current level of about 20pc.
An increase in gas-powered electricity equivalent to at least four or
five new large power stations is required, Eirgrid said.
ENDS
Notes: Download full submission
here:
Contact:
John McElligott - Tel.: 087-2804474 - Email:
[email protected]
www.SafetyBeforeLNG.ie